This three year project was designed to take a global approach to the traffic issues reported to our city counselperson. The committee of representatives from all areas of GPOA along with city engineers, traffic engineers and and a multitude of volunteer hours developed this piloting of a design that was met with mixed opinions. The piloting was implemented in 2014 and the final report took nearly a year to complete. Particular sections of the project were met with support that have resulted in the implementation of the District 1 design. All other areas were defeated on a global basis, although particular streets did have the support and could still result in implementation or continued discussion of potential changes to impact traffic patterns in the area.